20kV/150kV NIKAIA

20kV/150kV NIKAIA

The company took over on 6th of 2023

PROJECT IDENTITY :

20kV/150kV Voltage Raising Substation NIKAIA, in the Municipality of Kileler

CONTRACTOR : ARCHON - THERISSO ENERGY P.C.

PROJECT OWNER : UNITED ENERGY COMMUNITY P.C.

Subject :

Construction and erection of all Civil Engineering Works for the project of construction of the above mentioned new 20kV/150kV NIKAIA Voltage Raising Substation, in the Municipality of Kileler, Photovoltaic Park Connection in accordance with the relevant Studies and Plans, relevant permits, conditions and specifications of ADMIE.

COMPLETED & connected to the grid of ADMIE on 12th 2024